Estimating unknown tasks

Came across lots of good information on estimating unknown tasks in this stackexchange thread. Two main takeaways:

  1. Have you broken down the task into sufficient sub-tasks? The trouble with estimating may come from the fact that you are considering a large, complex task with many parts that you don’t fully understand. For example, “Build a shed”… the shed could be large, small, complex, simple: the trouble with estimating comes from insufficient thought about what the shed will be.
  2. D = ((1 * OD) + (4 * ED) + (1 * PD)) / 6

    • OD = Optimistic Duration
    • ED = Expected Duration (your best guess)
    • PD = Pessimistic Duration
    • D = Most likely duration

Leave a Reply

Fill in your details below or click an icon to log in: Logo

You are commenting using your account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s